Issuing of the building permit*
favorite_border
Add favorite
Procedure
Online
Companii
Cetateni
National
The building permit constitutes the final act of authority of the local public administration based on which the execution of construction works is permitted, according to the measures provided by law regarding the location, design, realization, operation, and post-use of constructions. The building permit is issued based on the documentation for authorizing the execution of construction works, prepared under the conditions of this law, on the basis and in compliance with the provisions of urban planning documentation, approved and endorsed according to the law. For the issuance of the BP, the applicant submits the application and BP in 2 copies to the Urban Planning Department of Satu Mare Commune City Hall together with proof of payment of the fee for issuing the building permit.
The process responsible analyzes the documentation and then prepares the Building Permit in 2 original copies and forwards it for signing. One copy of the BP remains in the archive alongside the documentation that was the basis for its issuance, while the second copy is handed to the applicant together with the documentation endorsed as unchanged.
- the request form and annex are filled in accordingly;
- the urban planning certificate is valid, and the purpose of its issuance coincides with the object of the application for authorization;
- there is proof of the applicant's title over the property, land and/or constructions, and, as the case may be, the excerpt from the cadastral plan and the information excerpt from the land register, updated to date, unless the law provides otherwise;
- the technical documentation - T.D. is complete and complies with the provisions of Annex no. 1 to Law
no. 50/1991, republished, regarding the authorization of construction works, with subsequent amendments and completions and methodological norms;
- there are favorable opinions and agreements and, as the case may be, the studies required by the urban planning certificate;
- there are project verification reports and, as the case may be, the technical justification note/expert report, energy audit report, technical systems expertise report, building energy performance certificate, as well as the study on the possibility of installing/using alternative energy production systems where applicable;
- proof of payment of the legal fees required for issuing the building/demolition permit is provided;
- the stamp issued by the Order of Architects of Romania, confirming the right of the architect/architectural conductor, as the case may be, to design and sign the documentation, is applied on the written and drawn pieces.
*Entitled persons
Regulated professions
Required documents
Denumire
Descriere
Obligatoriu
Semnătură digitală
Tip document
Descarcă
-
CF statement in original*
Descarcă
Scanned document
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Copy of urbanism certificate*
Descarcă
Scanned document
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
PT
EN*
Descarcă
Scanned document
Technical Project DTAC, DTAD, Site Organization*
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
The approvals requested through CU*
Descarcă
Scanned document
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Fee for issuing AC*
Descarcă
Scanned document
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
REQUEST for issuance of the building/demolition permit*
Descarcă
Formular tipizat
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Consent statement regarding the agreement for the processing of personal data*
Descarcă
Formular tipizat
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Fees
Title
Payment method
Value
Currency
Taxă variabilă
OP
Deadlines
Resolution time:
30
Calendar days
Case filling duration:
30
Calendar days
Notification deadline:
5
Calendar days
Legislation
Appeal routes
In the event of a dispute between the beneficiary and the competent authority, the provisions of common law shall apply.
*Additional information
More info:
Links
None
Assistance and problem-solving services
None
Last updated:
30 December 2021
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Institution responsible with document:
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Town Hall of Satu Mare Commune Harghita*
*Content marked with an asterisk (*) has been automatically translated and may not fully reflect the original meaning. For objective interpretation, please consult the Romanian version.
Town Hall of Satu Mare Commune Harghita*
Str. Principală, nr. 450
Telefon:
0266-245140
Fax:
0266-245-140
Email:
satumare@hr.e-adm.ro
Table of contents
Competent entities
Compartimentul urbanism, amenajarea teritoriului, protectia mediului,
gospodărie comunală
Share your opinion
Provide your opinion about the content of this page. You can leave acomment about what we can improve. You will not receive a response toyour comment. Use the contact form to clarify any questions regardingthe information and services available on this portal.
Did you find what you were looking for?
Help us improve