ANIF technical notice for obtaining the Building Permit for investment objectives located within the built-up area of the localities - for legal entities*
Online
Companii
National
Cross-border
The Central Unit or Territorial Branch for Land Improvement coordinates the procedural activity regarding the issuance of approvals in compliance with the legal provisions in force.
The validity period of the approval is 24 months; before the expiration of this period, a single extension of the approval can be granted, after a written request (submitted to the issuing ANIF unit at least 5 days before the expiration of the ANIF approval validity period for which the extension is requested) and its verification on site.
The extension of the approval will have a different registration number from the ANIF approval issuance register and is granted for a maximum period of 12 months; after this date, a new extension of the approval validity is not possible, the applicant will have to obtain, under the law, another ANIF approval.
ANIF issues the approvals within 30 days from the submission of the documentation.
Denumire
Descriere
Obligatoriu
Semnătură digitală
Tip document
Descarcă
Title
Payment method
Value
Currency
The national legislation does not contain special provisions; in the event of a dispute, the common law provisions apply.