Specialty notice ANIF FTIF Olt - for legal entities*
favorite_border
Add favorite
Procedure
Online
Companii
National
Cross-border
The Central Unit or Territorial Branch for Land Improvements coordinates the procedural activity regarding the issuance of approvals in compliance with the legal provisions in force.
*Entitled persons
Regulated professions
Required documents
Denumire
Descriere
Obligatoriu
Semnătură digitală
Tip document
Descarcă
-
The request of the beneficiary or the owner, as applicable, specifically mentioning the area, the investment to be made, signature*
Descarcă
Scanned document
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Copy of the identity document*
Descarcă
Scanned document
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Notarial power of attorney/delegation/general meeting decision of associations, decision of the sole associate/representative of the associative form, in copy, copy of the ID card of the authorized person, natural person, or a copy of the passport for the authorized natural person with domicile abroad*
Descarcă
Scanned document
In case of representation Following the notification of the issuance of the permit, when collecting it from the office, the documents must be presented in original*
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Copy of the ownership deed or another valid land possession document concluded, with notarized authentication closure*
Descarcă
Scanned document
Example: The title deed, sale-purchase contract, donation contract or concession contract, lease, rental, superficies will be presented.*
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Copy of the urbanism certificate (within the validity period), accompanied by the zoning location plan and the site plan*
Descarcă
Scanned document
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Technical documentation prepared by a certified and authorized person in land improvement works*
Descarcă
Scanned document
The technical solution regarding the protection of land improvement works, where the situation requires it. The documentation / technical project will also include the technical solution for the protection of land improvement works and will be checked according to the law, obligatorily by a certified project verifier.*
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Copy of the ANIF technical approval for obtaining the Building Permit or the ANIF technical agreement (as the case may be), for verifying compliance with the conditions imposed when issuing the approval*
Descarcă
Scanned document
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Proof of payment*
Descarcă
Scanned document
Payment can be made through the following methods: - cash at the Territorial Branch of Land Improvement Olt - payment order at the bank unit - treasury ANIF FT IF OLT ACCOUNT: RO20TREZ507501701X00441*
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Land registry excerpt*
Descarcă
Scanned document
The land register excerpt for information purposes, accompanied by the cadastral plan excerpt, issued by the cadastral and real estate publicity office no more than 30 days before the date of submission of the documentation, (except in the case where the construction permit is requested for the realization and rehabilitation of land improvement infrastructure in accordance with the provisions of art. 33, para. (2), letter a) of Law 138/2004 with subsequent amendments and completions).*
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Copies of payment documents*
Descarcă
Scanned document
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Fees
Title
Payment method
Value
Currency
None
Deadlines
Resolution time:
5
Calendar days
Case filling duration:
15
Calendar days
Notification deadline:
4
Calendar days
Legislation
- Law number
83
dated year
2018
ORDER no. 83 of February 23, 2018 for the approval of the Procedure regarding the permanent or temporary removal from the agricultural circuit of lands located outside the built-up area of localities, as well as for the approval of the Procedure regarding the refund of the fee paid to the Land Improvement Fund.*
- Law number
83
dated year
2010
Emergency Ordinance no.83 of 2010 regarding the exemption from the payment of the fees provided in art.42 para (3), letter h of the Land Improvements Law no.138 of 2004, for the removal from the agricultural circuit of land necessary for the realization of certain objectives of national, county and local interest*
Appeal routes
The legislation does not contain special provisions regarding remedies; in case of dispute, the common law provisions are applicable.
Additional information
More info:
Links
None
Assistance and problem-solving services
None
Last updated:
21 July 2022
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Institution responsible with document:
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Anif Territorial Branch for Land Improvements Olt*
*Content marked with an asterisk (*) has been automatically translated and may not fully reflect the original meaning. For objective interpretation, please consult the Romanian version.
Anif Territorial Branch for Land Improvements Olt*
Str. Vornicu Ureche, nr.15, Caracal, jud. Olt
Telefon:
0249515293
Fax:
0249512222
Email:
olt@anif.ro
Table of contents
Competent entities
Serviciul Tehnic, Investiţii, Achiziţii, Contracte
Share your opinion
Provide your opinion about the content of this page. You can leave acomment about what we can improve. You will not receive a response toyour comment. Use the contact form to clarify any questions regardingthe information and services available on this portal.
Did you find what you were looking for?
Help us improve