Request for the issuance of the permit regarding works for connections and branches to public networks of water, sewage, gas, and electrical energy*
Offline
Companii
Cetateni
National
Useful information for connection to the electricity distribution network (steps to follow):
-submission of the connection request and the necessary documents (request for issuance of Technical Connection Notice-ATR, request for site approval, documentation depending on the category of the construction or installation)
-establishing the solution for connection to the network
-issuance of the ATR - valid for 12 months from the date of issuance
-requesting the connection contract and choosing the operator who will design/execute the electrical installation
-design and execution of connection works. Execution works start only after:
a) the connection fee is paid,
b) the building permit for the objective is presented,
c) the building permit for the connection works is obtained,
d) a superficies/use/easement contract is concluded as applicable
-commissioning
-submission of the usage installation file
-issuance of the connection certificate
-final energizing and connection
*Denumire
Descriere
Obligatoriu
Semnătură digitală
Tip document
Descarcă
Title
Payment method
Value
Currency
In the case of a dispute between the beneficiary and the competent authority, the provisions of common law are applicable.