The request for extension of the validity of the construction/demolition permit must be submitted 45 working days before the expiry date, and according to the law, it can be granted only once for a maximum of 24 months.

For the extension of the validity of the construction/demolition permit, the applicant will create an account on the start.ps4.ro platform where they will submit a request for extension of the validity of the construction permit.

The value of the extension fee for the validity of the construction/demolition permit is 30% of the initial fee of the construction/demolition permit.

The payment of the fee can be made by bank transfer to account RO70TREZ70421160203XXXXX TREZORERIA SECTORULUI 4, SECTORUL 4 AL MUNICIPIULUI BUCUREȘTI, CUI 4316422, at SelfPay devices, and online when submitting the application.
*
Entitled persons
Regulated professions
Required documents

Denumire

Descriere

Obligatoriu

Semnătură digitală

Tip document

Descarcă


-
Application form fully and correctly completed*
Descarcă
Formular tipizat
Form - REQUEST for the extension of the validity of the building/demolition permit.*
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Building/demolition permit*
Descarcă
Scanned document
The original building/demolition permit*
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Fee for extension of validity of building/demolition permit*
Descarcă
Scanned document
The payment document for the extension fee of the validity of the building/demolition permit - 30% of the initial permit fee.*
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Justification memorandum*
Descarcă
Scanned document
Justification memorandum accompanied by photographic support regarding the necessity of extending the building permit, respectively the physical stage of the works carried out based on the building/demolition permit, as well as the works remaining to be executed until completion.*
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Issued documents

Denumire

Tip document

Descarcă


-
Extended validity construction/demolition permit*
Document obligatoriu
Semnatură digitală obligatorie
Se poate obține prin OOTS
Fees

Title

Payment method

Value

Currency


None
Deadlines
Resolution time:
30
Calendar days
Case filling duration:
10
Calendar days
Notification deadline:
1
Calendar days
Appeal routes
In the event of a dispute between the beneficiary and the competent authority, the provisions of common law shall apply.
*
Additional information
More info:
Links
None
Assistance and problem-solving services
None
Last updated: 
12 March 2025
Publicat de către: 
A paragraph is a self-contained unit of a discourse in writing dealing with a particular point or idea. Paragraphs are usually an expected part of formal writing, used to organize longer prose.
Institution responsible with document: 
Publicat de către: 
A paragraph is a self-contained unit of a discourse in writing dealing with a particular point or idea. Paragraphs are usually an expected part of formal writing, used to organize longer prose.
City Hall of Bucharest's District 4*
*Content marked with an asterisk (*) has been automatically translated and may not fully reflect the original meaning. For objective interpretation, please consult the Romanian version.
City Hall of Bucharest's District 4*
Strada George Coșbuc, nr. 6-16, cod poștal 040531
Telefon: 0219441
Fax:
Email: contact@ps4.ro
Table of contents

Competent entities

DIRECȚIA GENERALĂ DE URBANISM ȘI AMENAJAREA TERITORIULUI

This site is managed by the Romanian Digitalisation Authority and is an official website of the Romanian Government
Public Institutions
Need assistance?
EU Institutions
Info
PNRR. Finanțat de Uniunea Europeană
UrmătoareaGenerațieUE
© 2024 roepas.ro